DexaFlow / Industrial commissioning record
FAT/SAT daily progress & punch protocol
Offline field capture register · Revision 01 · Sample excerpt · Not a live plant record
- Project
- Vejle Plant 2 Commissioning (FAT/SAT)
- Site / area
- Vejle Plant 2 · sample excerpt
- Date
- 11 OCT 2026
- Technician
- Lead commissioning engineer
Document hash CRC-32 0x4B78E109
Commissioning blocked by external disciplines (3.5h lost) · 3 blockers
| Time | Photo | Tag | Issue / voice transcription |
|---|---|---|---|
| 14:02:11UTC | Photo placeholder | +TK1-LT01 | Analog level transmitter cable coiled behind frame Issue: Analog level transmitter cable coiled behind frame. Never landed on sensor head. Electricians signed off terminal X14 as complete. Suspected component: Terminal strip X14 Action required: EXTERNAL_BLOCKER OPEN |
| 09:14:22UTC | Photo placeholder | +P2-PE04 | Station 2 infeed photoeye is NPN sinking Issue: Station 2 infeed photoeye PE-04 is NPN sinking, drawings specify PNP sourcing. PLC digital input rack 1 slot 2 bit 4 never goes high. Suspected component: Wrong sensor part number Action required: EXTERNAL_BLOCKER OPEN |
| 11:32:05UTC | Photo placeholder | +S3-GS01 | Safety gate 03 door interlock misaligned Issue: Safety gate 03 door interlock mechanically misaligned. Tongue binds on entry. Vibrations trip Channel B on safety relay K04. Suspected component: Misaligned latch Action required: HW_REMEDIATION PUNCH |
OEE guarantees suspended until full clearing of mechanical defects. SI warranty does not cover scrap.